[ARCHIVED] 2025 Road Improvement Information and Updates

Steamroller

2025 Double Seal Coat Plus FOG Seal Road Work 

8/25/25 Update

Youngblood Paving was awarded the 2025 Double Seal Coat Plus FOG Seal Contract. The following roads will be double sealed starting 8/25: 

  • Ridge Rd; 
  • Legion Dr (Shields Driveway to end); 
  • Four Wheel Dr; 
  • Public Works Dr; 
  • McMorran Dr

2025 Road Asphalt Patch Work

Richland Township Public Works performs yearly asphalt patch work repairs to help extend the life of roads. The Public Works crew have members that are certified with flagger training that will perform traffic management in the area of work. Please be cautious around the crew performing the work, as there is various equipment and asphalt work being completed in the area.

 8/19/25 Update
Tentative patch work schedule for Tuesday, August 19th 

  • Dickey Road (east side of Meridian Rd)
  • State Road

2025 Road Paving Program

The Board awarded the lowest bidder (Shields Asphalt for mill and pave; and, Youngblood Paving for Seal Coat) for the 2025 road paving project during the April 16, 2025 public meeting:

Road Paving List

  • Bruton Dr; Carter's Grove Rd; Yorktown Dr; Raleigh Ct; Chowning Ct
  • Sandy Hill Rd; Penn Tree Dr; Packsaddle Trail (PennTree-Sandy Hill); Heckert Rd (S of Bakerstown)
  • Fairfield Dr; Grove Rd (Meridian to Phillips); Franklin Dr; Oakcrest
  • N. Pioneer Rd; Vista Vue Dr*(*Tabled); Oakcrest Dr; Beechnut (portion between N. & S. Woodland)

Double Seal Coat Plus Fog Seal List

  • Ridge Rd; Legion Dr (Shields Driveway to end); Four Wheel Dr; Public Works Dr; McMorran Dr

Updates:

4/25/25 Update: Work is tentatively scheduled to begin Monday 4/28 on Bruton Dr; Carter's Grove Rd; Yorktown Dr; Raleigh Ct; Chowning Ct

5/2/25 Update: Work is tentatively scheduled: 

Monday - Finishing binder asphalt in the Yorktown Plan.

Tuesday - Binder asphalt on North Pioneer

Wednesday - Wearing asphalt on North Pioneer. Milling of Heckert and Penn Tree.

Thursday - Wearing asphalt in the Yorktown Plan.

Friday - Wearing asphalt in the Yorktown Plan.

5/12/25 Update: Work is tentatively scheduled:

Monday (5/12) - No work

Tuesday, 5/13 - Milling of Packsaddle Trail

Wednesday, 5/14 - Milling of Sandy Hill Road. Binder asphalt paving on Penn Tree Drive and Packsaddle Trail.

Thursday, 5/15 - Milling of Grove Road and Franklin Drive. Binder asphalt paving of Packsaddle Trail.

Friday, 5/16 - Binder asphalt paving on Sandy Hill Road.

5/16/25 Update: Work is tentatively scheduled:

Monday, 5/19 - Milling - Fairfield Drive

                       Binder asphalt - Sandy Hill Road

Tuesday, 5/20 - Milling - Oakcrest Drive

                       Wearing asphalt - Bruton Drive

                       Binder asphalt - Grove Road and Franklin Drive

Wednesday, 5/21 - Base Repair - Oakcrest Drive

                            Wearing asphalt - Carters Grove Road, Chowning Court, Grove Road and Franklin Drive

Thursday, 5/22 - Wearing asphalt - Yorktown Drive and Raleigh Court

                         Binder asphalt - Fairfield Drive

Friday, 5/23 - Wearing asphalt - Penn Tree Drive, Packsaddle Trail and Fairfield Drive

5/22/25 Update: Work is tentatively scheduled:

Friday 5/23 - Binder Asphalt on Oakcrest Drive and Fairfield Drive

Tuesday 5/27 - Wearing Asphalt on the Yorktown Plan roads

Wednesday 5/28 - Wearing Asphalt on Grove Road, Franklin Drive and Fairfield Drive

Thursday 5/29- Wearing asphalt on Packsaddle Trail and Penn Tree Drive

Friday 5/30 -Wearing Asphalt on Sandy Hill Road

This project will be a significant upgrade to the existing roads. Besides milling the full width of the road to a depth of approximately 3 l /2", the contractor will test the strength of the road base and make any necessary repairs up to a depth of 12". Deteriorated storm drain inlets will be replaced or repaired. Once the base work is complete, two layers of new asphalt will be installed. After work is completed, Township road crew will back-fill against the curbs and restore the adjacent berm/lawn areas as soon as possible. 

Due to their proximity to the edge of the pavement, some mailboxes will have to be moved. During construction, the contractor will attempt to temporarily install the mailboxes. Once construction is completed, the contractor will install the mailboxes in their permanent locations. During construction, it is possible that mail and waste collection· services may be disrupted. Your patience in this regard is greatly appreciated.

During construction, please comply with the following:

 NO ON-STREET PARKING DURING CONSTRUCTION. It is critical that the paving machinery be able to move freely on the roadways. If a vehicle is in the way, it will be towed.

  • Be sure to follow the flagmen's instructions and work zone signage.
  •  During the time between the milling and paving, motorists should take appropriate precautions to drive SLOWLY AND CAREFULLY to prevent damage to vehicles and surrounding property.
  •  Please avoid driving on freshly paved surfaces. Once marred, the quality of the paving job cannot be restored to its original standard.
  •  The Township Engineer, Shoup Engineering, will be on-site during most project hours. Any questions should be communicated with Shoup Engineering, not the paving crew workers. 
  • As with any construction project, some inconveniences should be expected. Although some traffic stoppage will be required, the contractor will try to keep it to a minimum.

Thank you for your patience!